Railton Neighbourhood logoRailton Neighbourhood

Milestones

  • Temporary Traffic Order

    June 2020

     

    -

     

    Complete

  • Experimental traffic order

    January 2021

     

    -

     

    Complete

  • Statutory objection period

    January 2021

     

    -

     

    June 2021

  • Formal consultation

    September 2021

     

    -

     

    Complete

  • Consultation ends

    October 2021

     

    -

     

    Complete

  • Decision to make Railton scheme permanent

    January 2022

     

    -

     

    Complete

  • Phase 1 building work commences at Atlantic Road

    March 2022

     

    -

     

    Complete

  • Phase 1 building work at Rattray and Dalberg Road

    March 2022

     

    -

     

    Completed

  • Engagement on Phase 2 designs

    May 2022

     

    -

     

    July 2022

  • Phase 2 works at Shakespeare Road, Railton Road South and St Matthew's Road to commence

    December 2022

     

    -

     

    In Progress